move to the org document

pull/2338/head
yann300 3 years ago
parent 2371dce213
commit cfdab8c387
  1. 33
      release-management-flow.md
  2. 36
      release-management.md

@ -1,33 +0,0 @@
This document aims to help the release manager managing the release.
# pre release planning
- [ ] create a new project and prioritize issues / bugs with the team lead and according to the current roadmap.
- [ ] check with the team lead if this needs an intermediate release (intermediate release should be 2-3 weeks max).
- [ ] a release kickoff meeting with the team aiming to get input from everyone and modify the project accordingly.
- [ ] 2-3 days span where team members estimate their issues.
- [ ] a release planning meeting where we agree on the release scope (intermediate and/or classic release).
- [ ] after this meeting: all the issues / PR should have been qualified in term of effort and scope.
- [ ] after this meeting: date for feature freeze, QA period, and release date should be set in the project title.
# coding period
- [ ] 10 min after each daily standup where the release manager give an update of the current situation and ETA.
- [ ] release manager should make sure to be aware of the current state of each issues ans PRs during the coding period, so he/she can best provide support.
# QA preparation
- [ ] prepare the internal QA document, assign team members.
- [ ] prepare the external beta test document for beta testers.
- [ ] 1 week before QA period, start engaging with beta testers and online.
# feature freeze, QA period.
- [ ] publish to remix-beta every day.
- [ ] merge reviewed PRs.
- [ ] a QA open sync meeting where we all do our assigned tasks.
# post release
- [ ] retrospective meeting.

@ -64,6 +64,42 @@ The release manager is still responsible for ensuring a project is rolled out sm
- During feature freeze, remix-beta should be updated every morning.
- A meeting with Andy and Rob should be organized for ensuring the beta test results are properly handled.
## check list:
### pre release planning
- [ ] create a new project and prioritize issues / bugs with the team lead and according to the current roadmap.
- [ ] check with the team lead if this needs an intermediate release (intermediate release should be 2-3 weeks max).
- [ ] a release kickoff meeting with the team aiming to get input from everyone and modify the project accordingly.
- [ ] 2-3 days span where team members estimate their issues.
- [ ] a release planning meeting where we agree on the release scope (intermediate and/or classic release).
- [ ] after this meeting: all the issues / PR should have been qualified in term of effort and scope.
- [ ] after this meeting: date for feature freeze, QA period, and release date should be set in the project title.
### coding period
- [ ] 10 min after each daily standup where the release manager give an update of the current situation and ETA.
- [ ] release manager should make sure to be aware of the current state of each issues and PRs during the coding period in order to have a better overview of who is working on what and best provide support to all the team members that are involved in the release.
### QA preparation
- [ ] prepare the internal QA document, assign team members.
- [ ] prepare the external beta test document for beta testers.
- [ ] 1 week before QA period, start engaging with beta testers and online.
### feature freeze, QA period.
- [ ] publish to remix-beta every day.
- [ ] merge reviewed PRs.
- [ ] a QA open sync meeting where we all do our assigned tasks.
### post release
- [ ] retrospective meeting.
## Assignments:
Aniket, Liana, David, Rob, Filip, Yann

Loading…
Cancel
Save